While the brickwork still isn't progressing the interior has been moving in leaps and bounds. The waterproofing is going in the wet areas, and the tiles have been delivered, and are ready for installation in the bathrooms and laundry area. The ceiling scotia has been completed throughout the house. No sign of the skirting boards yet, but I'm not sure if they're waiting for the floor tiles to go in before doing that? Rob was saying she'd seen the kitchen fitout being delivered the other day, so that could well be in soon too. The brickwork should be resuming soon, since the Termimesh looks like it's finally been installed, and glass pieces have been poured into the footing spaces around the pad and behind the base layer of bricks.